Chinese New Year 2027

Chinese New Year 2027: What Does It Mean for Import Planning?

Find out what to consider when placing orders, reviewing stock levels and arranging transport so you can keep supplies flowing and meet your delivery commitments.

Chinese New Year 2027 falls on 6 February, eleven days earlier than in 2026. For businesses importing from China, the earlier date makes it especially important to plan orders, confirm suppliers’ schedules and coordinate transport before the end of 2026.

Operations can be affected before the festivities begin and for some time afterwards. Production slowdowns, factory closures and a gradual return to normal operations can affect when goods are ready and when they can be shipped.

For a business owner, the practical question is simple: will the goods you need in early 2027 arrive on time?

The answer depends on how well you coordinate purchasing, production, stock management and international transport. Here is what to check when planning your imports.

 

Why plan ahead for Chinese New Year 2027?

Chinese New Year affects factories, suppliers and logistics services. Major shipping lines typically issue notices about changes to their operations during this period. It is worth taking those changes into account when planning shipments and assessing alternatives.

In 2027, the shorter gap between the December holidays and Chinese New Year leaves less time in January to deal with outstanding orders or adjust supply arrangements.

Each supplier sets its own closure dates. Deadlines for accepting orders, completing production and dispatching goods can vary, as can the date when operations resume.

Base your import plans on dates confirmed for each shipment.

 

1. Work backwards from the date you need the goods

Start by establishing when the goods need to be available at your premises.

That date depends on what you need them for. You may have a production run scheduled, stock to replenish, a product to launch or a delivery promised to a customer.

Work backwards from that date, allowing time for each stage:

  • Final delivery and receipt of the goods
  • Customs clearance and any inspections
  • Unloading and handling at destination
  • International transport and any transhipments
  • Collection at origin and preparation for dispatch
  • Production and release of the order for collection by the supplier

Production completion and delivery are two separate milestones. Once an order is ready at the factory, it still has several stages to go through before you can use or sell the goods.

Agree a suitable buffer with your logistics partner, taking into account the route and how critical the goods are to your business.

 

2. Confirm your suppliers’ production schedules and closure dates

When importing from China in 2027, ask for specific dates. A general estimate of availability gives you little to work with when arranging collection or promising a delivery date.

Ask each supplier to confirm the following, preferably in writing:

  • The last date for placing an order that can be produced before the shutdown
  • The expected completion date for your order
  • The date the goods will actually be ready for collection
  • The closure dates for both the factory and the warehouse
  • The expected dates for production and dispatch to resume

Check whether your order depends on materials or components from other manufacturers. Your supplier may still be operating while facing shortages further up the supply chain.

Even after the factory reopens, your order may take time to become available. Allow for a gradual return to normal production when setting your purchasing schedule.

 

3. Review stock levels and prioritise critical items

Preparing for Chinese New Year does not require an increase in every order.

Excess stock can tie up capital and take up warehouse space with slow-moving products. Focus on the items whose absence would have the greatest impact on your business.

For each critical product or material, assess:

  • Current stock levels
  • Forecast usage or demand
  • Confirmed orders and goods in transit
  • Replenishment lead time
  • Availability of alternative suppliers
  • Consequences of a stockout

A low-cost component may deserve priority if its absence would prevent you from completing an entire order.

The aim is to hold enough stock to keep the business running, taking commercial, operational and financial needs into account.

 

4. Check your import plans against your export commitments

Chinese New Year can also affect Portuguese exporters.

A manufacturer in Portugal may rely on components, raw materials or packaging from China. If those supplies arrive later than expected, production schedules and deliveries to international customers may be at risk.

This dependency can exist even when you buy from a European distributor.

Before committing to a delivery date, ask three questions:

  1. Are the materials we need available?
  2. Can we rely on the arrival dates given for outstanding orders?
  3. Do we have an alternative if a critical component does not arrive on time?

Having purchasing, production and sales teams review these dates together helps identify problems while there is still time to act.

 

5. Plan transport before the goods are ready

Involve your logistics partner as soon as you have reliable estimates for the shipment.

To assess your international freight options, share the following details:

  • Collection point and destination
  • Description and characteristics of the goods
  • Quantity, weight, volume and dimensions
  • Expected date when the goods will be ready for collection
  • Required delivery date
  • Agreed purchase terms, including the applicable Incoterms® rule
  • Any special handling or documentation requirements

With this information, your logistics partner can assess sea and air freight options, compare routes and consider whether to split the shipment.

For example, it may make sense to bring forward a critical part of the order and use a service with a longer transit time for the remainder.

How far ahead you need to book depends on the shipment. Confirm the booking lead time for your specific origin, destination, service and shipping dates.

 

6. Check the documentation before shipment

Even an order completed on time can run into difficulties if documents are missing or contain conflicting information.

Before shipment, check with the parties involved which documents and requirements apply to the goods.

Depending on the product and the shipment, this may mean checking the commercial invoice, packing list, importer details, tariff classification and any certificates or authorisations required.

Checking before departure gives you time to correct omissions or discrepancies that might otherwise come to light only when the goods arrive.

 

Checklist: is your business ready?

Before finalising your import plans for the first quarter of 2027, check that you have:

  • Identified critical products and materials
  • Established when you need the goods at your premises
  • Obtained your suppliers’ schedules
  • Confirmed production and collection dates
  • Compared available stock and goods in transit with forecast demand
  • Discussed your requirements with your logistics partner
  • Checked the documentation required for each shipment
  • Prepared alternatives for your most time-sensitive commitments

Plan your imports with WLP

Planning for Chinese New Year 2027 starts with understanding what your business needs and coordinating with suppliers, internal teams and logistics partners.

Making these decisions early gives you more time to assess your options, reduce the risk of stockouts and meet the commitments you have made to customers.

At WLP – Worldwide Logistics Portugal, we help you assess each shipment and plan transport around your goods, deadlines and business objectives.

Are you planning to import from China, or does your business rely on materials sourced there? Speak to our specialists about your upcoming shipments.

 

 

Frequently asked questions about Chinese New Year 2027

When is Chinese New Year 2027?

Chinese New Year falls on 6 February 2027. Confirm closure and reopening dates with each supplier, as they may differ from the official holiday period.

When should I place my order to receive goods before Chinese New Year?

That depends on production lead time, transit time and your required delivery date. If you need goods in early 2027, assess your requirements before the end of 2026. Work backwards from the date the goods need to be available at your premises to determine when to place the order.

How long do factories in China close for?

Closure periods vary from one factory to another. Suppliers may start reducing output at different times before the holiday and may take different lengths of time to return to normal capacity. Check when warehousing and dispatch services will be available as well.

Can Chinese New Year affect sea and air freight?

Yes. Changes in production schedules and in the dates when cargo is ready can affect planning for both modes of transport. Confirm service options, available capacity and transit times for each shipment.

Should I increase stock levels before the holiday?

It may make sense to hold more of certain critical items. Base the decision on forecast demand, replenishment lead times and the impact of running out. Assess the need for each product before increasing order quantities across the board.

My business exports from Portugal. Should we prepare as well?

Yes, if you rely on raw materials, components or packaging from China. A supply delay can affect production in Portugal and deliveries to your international customers.